Inspection Request
For Civil / Structural Works
The
Engineer
|
The
Contractor
|
|||||||||||||||
Project:
|
||||||||||||||||
From: (Contractor's Name)
|
To: #####Consult
|
|||||||||||||||
Inspection
Request
For Civil / Structural Works |
IR No. :
|
Civil / IR /### - Rev.00
|
||||||||||||||
Date :
|
||||||||||||||||
Inspection
Required on: |
Date:
Time:
|
|||||||||||||||
Subcontractor:
|
||||||||||||||||
Type of
Work : |
Received by Consult:
Signature : Date : Time : |
|||||||||||||||
Location of Inspection :
|
||||||||||||||||
Elements to be inspected : (enclosed highlighted copy of the relevant drawing(s)
in A4 size) :
|
||||||||||||||||
Subcontractors' Signature &
Date :
|
||||||||||||||||
HVAC :
|
Electrical :
|
|||||||||||||||
Plumbing & F.F. :
|
Elevators :
|
|||||||||||||||
Contractor's Signature & Date
:
|
||||||||||||||||
Safety Officer :
|
QA / QC Engineer :
|
|||||||||||||||
Construction Manager :
|
||||||||||||||||
The above mentioned Works have
been checked, coordinated and found complying with the approved shop drawings
& Contract Documents
|
||||||||||||||||
Inspection
Status
|
||||||||||||||||
Engineer's Representative Comments
:
|
||||||||||||||||
Engineer's Representative :
Signature & Date |
Received By Contractor :
Signature & Date |
|||||||||||||||
Checking and approval by the
Consultant / Sub-Consultant shall not relieve the Contractor of his
obligations to perform the Work in accordance with the approved shop drawings
and Contract Documents and the Requirements of Safety and Local Authorities'
regulations
|
No comments: