Response Sheet
Response Sheet
|
|||
WIR Ref - 2790 Rev.02
|
Dated :
17-Nov-2018
|
||
S/No.
|
Consultants Comments
|
Contractors Reply
|
|
1
|
ATS to SMDB and ATS to MDB 2A ECC cable not complete
|
ATS to SMDB and ATS to MDB 2A ECC cable to be complete
|
|
2
|
Earth continuity maintained all joints
|
Earth continuity maintained to be all joints
|
|
3
|
Cable trays joints proper tight and gapes rectify
|
Cable trays joints proper tight and gapes to be rectify
|
|
4
|
Cable trays alignment
|
Cable trays alignment to be properly
|
|
5
|
Cable trays supports not properly fixed
|
Cable trays supports
properly fixed
|
|
6
|
Cable trays site fabricated accessories not acceptable
|
Cable trays in site fabricated accessories not use
|
|
7
|
|||
8
|
|||
9
|
|||
10
|